Efacec’s Automation business area received from Sonelgaz, the Algerian company for generation, transmission and distribution of electric power, a set of important orders with a total amount around 4.3 million euros, for the supply of substation automation systems for 4 new substations of GRTE (the electric power transmission company from Sonelgaz). The substations are the following ones: Tissemsilt (220/60 kV), Messerghine (220/60 kV), Thniet El Had (60/30 kV) and Sidi Kada (60/30 kV).
The Efacec’s scope of supply for the two transmission substations (220/60 kV) comprises two automation systems, based on the CLP 500SCC platform, integrating Efacec’s BCU 500 bay control units, as well as protection systems from Efacec (TPU 420 family) and from third parties. |